Saturday, July 26, 2008

Estimated times after last night DBA activities

As estimated by the time it took from yesterdays import/export activities the tasks planned on line 42 and 43 should take 1.5 hours less then planned.

Activities 44 and following should start 1.5 hours earlier.

An update will follow once activities 36 to 38 will be completed.

NOTE: the bridge is not open as planned.